Pile installation

EAZET is an environmentally friendly pile method with low noise, low vibration, and no waste soil. The installation process is extremely simple. Works by a compact machines less than 10m height are safe and executing speedy pile installation.

EAZET pile Standard installation Process

steel pipe pile, screw pile, installation
  • 1. Attach a pile to torque motor
  • 2. Set the pile to the planned location.
  • 3. Begin rotation while applying downward crowd
  • 4. Add extension sections if necessary
  • 5. Completion of the pile installation

EAZET work on site

Standard EAZET installation

  • 1.Delivering the pile machine., steel pipe pile, screw pile

    1. Delivering the pile machine.

  • 2.Bringing in the EAZET pile machine to the site.

    2. Enter the construction site.

  • 3.Unloading EAZET piles.

    3. Deliver EAZET piles.

  • 4.Setting the EAZET pile.

    4. Setting the EAZET pile.

  • 5.Centering of pile.

    5. Centering of pile.

  • 6.EAZET pile construction without wastage.

    6. EAZET pile installation without waste soil.

  • 7.Connecting the piles(Type of CCJ at this site).

    7. Connect the piles.

  • 8.Installation of extension piles.

    8. Continue or finish the installation.